CityGate Overview
The residential complex CityGate is about to be completed: Two further buildings with a total of almost 200 apartments and additional attractive offers for residents are currently being constructed on the site.
In 2001, the Basellandschaftliche Pensionskasse acquired the former MIBA site between the SBB railway station and the St. Jakob Park. The site was divided into four sections, two of which have already been developed: On construction site C there is a building mainly used for offices, while on construction site D the Senevita Gellertblick residence offers retirement and nursing homes. From September 1, 2020, 117 new apartments will be ready for occupancy in building A and 78 in building B from October 1, 2020, . The new apartments will be located in the new building.
2001
Acquisition of MIBA site by Basellandschaftliche Pensionskasse
2002/2003
Study on the use of the site commissioned
2008/2009
Realisation of building C by Diener & Diener Architects
2009
Development plan for plots A and B submitted for approval
2012/2013
Realisation of Building D by Luca Selva Architects
2019
Laying of the foundation stone for houses A and B
2020
Fist occupancy of rental flats from September Haus A and from October Haus B